construction update smallVisit 07

Date : Friday 30th November

Weather : Temp 4.5°C, Heavy rain with sunny spells.

Principal Contractor : Compass Building & Construction Services Ltd

Site Manager : Robbie Tewnion & Jake Reid

Site Personnel

1 Site Manager + 1 Trainee Site Manager 0 Electrician 0 Lorry driver removing spoil 0 Ecologist 3 Groundworkers 0 Brick laying squad 0 Site Engineer

Sub Contractors Appointed

Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer

Activities on site

Initial site establishment is in place. Toilets and welfare are available for use by site personnel. Foundations have commenced.

Substructure blockwork is now substantially complete with spaces left for casting the extensions for the Glulam HD bolt pads.

Dowels for tying the pad extensions to the pad founds remain to be installed.

Shuttering for the pad extensions remains to be installed.

Fairhurst have been consulted regarding subsoil percolation rates. Fairhurst have confirmed ground conditions are as expected and soakaways can proceed as per the design.

  • The full report includes photos and diagrams which can't easily be separated from their original PDF format. Click HERE to view the full report.
  • An archive of these construction updates is available HERE.

Book our Facilities

Use the online booking system to check availablity and request a booking for Tomatin Village Hall or the Sports Facility.

Booking Page

Contacts

site.manager@strathdearn.org

hall.manager@strathdearn.org

errors@strathdearn.org

Get Involved!
Would you like to contribute to the content on this website?