Strathdearn Community Website

construction update smallVisit 08

Date : Friday 7th December

Weather : Temp 5°C, overcast, raining

Principal Contractor : Compass Building & Construction Services Ltd

Site Manager : Robbie Tewnion & Jake Reid

Time Lost : 3 days lost to wet trades (3rd Dec 0°C, 4th Dec -1.5°C, & 5th Dec -7°C Dec)

Site Personnel

Site Manager + 1 Trainee Site Manager 2 Joiners 1 Lorry driver removing spoil 0 Ecologist 2 Groundworkers 0 Brick laying squad 0 Site Engineer

Sub Contractors Appointed

Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer Gartec Lift supplier & installer.

Activities on site

Initial site establishment is in place. Toilets and welfare are available for use by site personnel. Foundations have complete

Substructure blockwork is now substantially complete.

Joiners installing shutters for HD bolts for glulam frame. Ensure all extension shutter boxes are cleaned of rubble, drilling dust etc prior to casting.

Dowels for tying the pad extensions to the pad founds are being installed.

Excavations for parking soakaways are being undertaken adjacent to the road. Spoil is being disposed of locally.

  • The full report includes photos and diagrams which can't easily be separated from their original PDF format. Click HERE to view the full report.
  • An archive of these construction updates is available HERE.

 

Book our Facilities

Use the online booking system to check availablity and request a booking for Tomatin Village Hall or the Sports Facility.

Booking Page

Contacts

site.manager@strathdearn.org

hall.manager@strathdearn.org

errors@strathdearn.org

Get Involved!
Would you like to contribute to the content on this website?