construction update smallTomatin Community Hub

Visit 11

Date : Tuesday 8th January 2019

Weather : Temp 5°C, Dry, slightly overcast

Principal Contractor : Compass Building & Construction Services Ltd

Site Manager : Robbie Tewnion & Jake Reid

Time Lost : 3 days lost to wet trades (3rd Dec 0°C, 4th Dec -1.5°C, & 5th Dec -7°C)

Site Personnel

1 Site Manager + 1 Trainee Site Manager 0 Joiners 0 Lorry driver removing spoil 0 Ecologist 2 Groundworkers 6 Concrete Squad 1 Brick laying squad 0 Site Engineer

Sub Contractors Appointed

Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer

2

Activities on site

Bolt pads have been stripped and bolts have been loosened and are free within the cones. Pads have been put back over the bolts to keep the pockets clean and free of debris.

Plinth for the base of the pre cast stair has been cast. Dowels have been cast in to the pad for continuity with the slab pour when it happens.

The 1st lift of blockwork forming the stair enclosure has been built. The remaining blockwork will be built after the GF slabs have been cast.

Joiners have now formed and installed internal shutters on top of the bolt pads to allow the floor slabs to be cast up to the bolt pads.

Drain pop ups and service ducts have been installed and preparation for GF slab pours. Drains have been tested and witnessed by R Tewnion.

DPM and insulation being laid in preparation for GF Slab pour.

The dpm at bolt pad extensions should be lapped up the side of the concrete extensions and sealed around the concrete to ensure the damp proofing is continuous around the pads.

Insulation should have a minimum 500 gauge polythene or visqueen isolation layer laid between the concrete and the foil face of the insulation as per the manufacturer’s instructions (extract below and full Datasheet appended). This is to protect the foil surface from reacting with the alkaline concrete.

3

Upcoming Activities

Complete dpm, underfloor & perimeter insulation.

Cast GF Slabs.

Erect scaffold and complete blockwork to the stairwell, install precast and complete stair blockwork.

Glulam delivery scheduled for 21st January provisionally. May move back depending on progress.

Progress car park works.


  • The full report includes photos and diagrams which can't easily be separated from their original PDF format. Click HERE to view the full report.
  • An archive of these construction updates is available HERE.


Book our Facilities

Use the online booking system to check availablity and request a booking for Tomatin Village Hall or the Sports Facility.

Booking Page

Contacts

site.manager@strathdearn.org

hall.manager@strathdearn.org

errors@strathdearn.org

Get Involved!
Would you like to contribute to the content on this website?