construction updateVisit 04

Date : Thursday 8th November

Weather : Temp 9°C, clear, sunny

Principal Contractor : Compass Building & Construction Services Ltd

Site Manager : Robbie Tewnion & Jake Reid

Site Personnel

1 Site Manager 0 Electrician 1 Lorry driver (to remove playpark equipment) 0 Ecologist 2 Groundworkers

Sub Contractors Appointed

Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install.

Activities on site

Initial site establishment is in place. Toilets and welfare are available for use by site personnel.

Soil has been stockpiled for removal from site.

Borrowpit used to generate general fill which is being spread across the Hub footprint ready for digging through to form foundations.

Foundations will be cast w/c 12th November and substructure blockwork is due to commence Thursday 15th November.

Playpark has been dismantled and removed off site for safe keeping. One or two timber elements will require to be replaced and Compass have retained fixings and a file of photos for use when re assembling the play equipment in the future.

update pic 3

update pic 4

update pic 5

update pic 6

 

Book our Facilities

Use the online booking system to check availablity and request a booking for Tomatin Village Hall or the Sports Facility.

Booking Page

Contacts

site.manager@strathdearn.org

hall.manager@strathdearn.org

errors@strathdearn.org

Get Involved!
Would you like to contribute to the content on this website?