construction update smallVisit 05

Date : Friday 16th November

Weather : Temp 5°C, clear, sunny

Principal Contractor : Compass Building & Construction Services Ltd

Site Manager : Robbie Tewnion & Jake Reid

Site Personnel

1 Site Manager + 1 Trainee Site Manager 0 Electrician 1 Lorry driver removing spoil 0 Ecologist 3 Groundworkers 1 Site Engineer

Sub Contractors Appointed

Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer

Activities on site

Initial site establishment is in place. Toilets and welfare are available for use by site personnel.

Soil has been stockpiled on site and being removed.

Foundations have commenced. Dowel bars to be drilled in at some junctions. Ensure dowel embedment depth is to engineer’s design.

Where mesh tails have been left for overlapping mesh to be tied to ensure sufficient lap length (350mm minimum or 2 squares of mesh) to be left for next section to be tied to.

Substructure blockwork is now due to commence Wednesday 21st November.

[The full report includes photos and diagrams which can't easily be separated from their original PDF format. Click HERE to view the full report.]

Book our Facilities

Use the online booking system to check availablity and request a booking for Tomatin Village Hall or the Sports Facility.

Booking Page

Contacts

site.manager@strathdearn.org

hall.manager@strathdearn.org

errors@strathdearn.org

Get Involved!
Would you like to contribute to the content on this website?