Strathdearn Community Hub : Construction Update #39

construction update smallDate : w/e 28th July 2019 

Weather : Temp 19°C, warm and predominantly dry, some drizzle. 

Principal Contractor : Compass Building & Construction Services Ltd 

Site Manager : Robbie Tewnion / Archie Cameron MacKintosh 

Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be 

determined by Client’s Representative. Site Personnel 

1 Site Manager 5 Joiners 0 Plasterer + 0 Apprentice 3 Mechanical (Crudens) 3 MH Electrical 6 Groundworkers 0 Scaffolders 1 Labourer 0 painters 2 Lightning Protection 

Sub Contractors Appointed 

Shane MacLennan Groundworks EastWest Flooring Concrete Screed Scotframe Kit supply & design Swarco EV Charging Glulam Solutions Kit and glulam erection Standard Patent Glazing Roof Lights FP McCann Precast concrete supply Pat Munro Water & Fire Mains C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation Highland Scaffolding Scaffolding Highland Decorating Taping & Decorating 

2 

Activities on site 

Labour numbers on site remain lower than woulfd be expected due to holidays. 

The blockwork forming the stair enclosure has been completed and the fireproof cap has been built. The perimeter of the capping has now been fire sealed to the viewing gallery side. The meeting room side remains to be fire stopped. Still the case. 

The final installation of diagonal bracing remains to be completed in the main hall. 

Wall cladding is complete with window seals and timber ingos to be fitted. The upper level boards have been overcoated and the finish is looking far more even. Grilles have been installed over the smaller plenum boxes. 

Now that the scaffold has been dropped on the West elevation numerous paint runs on the low level narrow cladding boards can be seen. These will have to be flattened and re coated. Discussed with Chud and Archie on site who are aware and steps will be taken to make good 

1st fix electrical works are complete, back boxes are being fitted and sub mains boards being wired in. boxing out of the sockets, switches etc is on going. Grommets have been fitted in the metal back boxes where cables enter the box. 

Plumbers have completed 1st fix plumbing and heating pipework runs above the shower and changing areas as well as above ceiling level at the Youth Group/ room room and Viewing Gallery/Lighting Control. The ceilings in the shower/changing areas are being insulated and sheeted. Internal partition erection is ongoing through the GF changing areas. 

UFH pipework is being installed at the 1st floor. Screed has been laid across the pipes. Some pipe clips visible above the screed and may interfere with laying chipboard. 

Exhaust and Fresh Air inlet Plenum boxes have been installed into the west elevation gable. Ducts to the main plenum boxes are in the process of being installed in the plantroom. The air handling plant has been installed and ducting between the units is ongoing. 

Main hall plasterboard is complete and access corridor plasterboarding is ongoing. 

Recent heavy rain has identified 2 leaks from the opening sashes of the recently installed roof lights. 1 in the hall and one in the corridor. The manufacturer is visiting site next week to make good the seals. 

The water and fire mains installations from the point of connection to the building is ongoing. A date for connection to the supply main remains to be agreed. 

The trenches for the lightning protection tapes have been excavated and the copper tapes and rods installed to complete the lightning earthing system. Copies of test and resistance certificates to be issued. 

Bases for the ASHP and the SSE transformer have been cast. SSE haved been on site to arrange transforner installation. 

Taping & filling remains to start. Was scheduled for w/c 22nd July but did not happen. Ensure any holes in plasterboard between plant room and corridors are filled to prevent noise transmission from plant areas (See photo below). Ensure abortive holes in ceilings or walls are properly patched. 

3 

Bats were witnessed during the 2nd survey. 1 or 2 bats were noted flying around outside and 1 inside. The millenium hall does not appear to be a maternity roost or require further surveys. The ecologist will report fully by the 10th of August. 

The fire fighting water supply tank has been delivered to site. 

Remove air extract grille in hall above viewing gallery opening to allow plasterboard to be taped and filled. 

Rainwater drainage pop ups and runs have commenced. 

Upcoming Activities 

Complete M&E 1st fix. Complete Fire capping edge seals over stair well. Install chipboard flooring to 1st floor level Make good cladding finishes. Complete plasterboard to GF ceilings and partitions to GF areas. Progress internal Tape & Fill Progress external watermain and SSE power mains Progress stormwater drainage runs Backfill lightning tapes around building perimeter. Install transformer Commence decoration.


  • The full report includes photos, tables and diagrams which can’t easily be separated from their original PDF format. Click HERE to view the full report.
  • An archive of these
    construction updates is available HERE.

Temporary Hall Closure

millennium hall closureCompass need to start work soon on external groundwork for the Hub building which will severely hamper their space for work vehicles. After consultation with user groups, SCD has agreed to close the Millennium Hall from Monday the 12th of August to Thursday the 22nd of August to allow Compass to complete this essential work quickly, safely and efficiently.

Compass will make their welfare facilities available to passing travellers during the hall closure.

Strathdearn Community Hub : Construction Update #38

construction update smallDate : w/e 21st July 2019 

Weather : Temp 19°C, warm and predominantly dry, some drizzle. 

Principal Contractor : Compass Building & Construction Services Ltd 

Site Manager : Robbie Tewnion / Archie Cameron MacKintosh 

Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be 

determined by Client’s Representative. Site Personnel 

2 Site Manager 6 Joiners 0 Plasterer + 0 Apprentice 2 Mechanical (Crudens) 1 MH Electrical 5 Groundworkers 0 Scaffolders 0 Labourer 0 painters 0 Roofers 

Sub Contractors Appointed 

Shane MacLennan Groundworks EastWest Flooring Concrete Screed Scotframe Kit supply & design Swarco EV Charging Glulam Solutions Kit and glulam erection Standard Patent Glazing Roof Lights FP McCann Precast concrete supply Pat Munro Water & Fire Mains C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation Highland Scaffolding Scaffolding Highland Decorating Taping & Decorating 

2 

Activities on site 

Labour numbers on site are lower than usual due to holidays. 

The blockwork forming the stair enclosure has been completed and the fireproof cap has been built. The perimeter of the capping has now been fire sealed to the viewing gallery side. The meeting room side remains to be fire stopped. Still the case. 

The final installation of diagonal bracing remains to be completed in the main hall. 

Wall cladding is complete with window seals and timber ingos to be fitted. The upper level boards have been overcoated and the finish is looking far more even. Grilles have been installed over the smaller plenum boxes. 

Now that the scaffold has been dropped on the West elevation numerous paint runs on the low level narrow cladding boards can be seen. These will have to be flattened and re coated. Discussed with Chud and Archie on site who are aware and steps will be taken to make good 

1st fix electrical works are complete, back boxes are being fitted and sub mains boards being wired in. Little further progress on the electrics in the last week due to holidays. 

Plumbers have completed 1st fix plumbing and heating pipework runs above the shower and changing areas as well as above ceiling level at the Youth Group/ room room and Viewing Gallery/Lighting Control. The ceilings in the shower/changing areas are being insulated and sheeted. Internal partition erection has commenced with cables being dropped into the partition and the walls are being sheeted. 

UFH pipework is being installed at the 1st floor. Screed is likely to be laid towards the end of next week. 

Exhaust and Fresh Air inlet Plenum boxes have been installed into the west elevation gable. Ducts to the main plenum boxes are in the process of being installed in the plantroom. The air handling plant has been installed and ducting between the units is ongoing. 

M&E 1st Fix estimated as being 85 – 90% complete. 

Main hall and access corridor plasterboarding is nearing completion. Monitor fixing centres at sheets on ceilings. Should be 230mm generally and at 150mm centers at board ends. 

Gutter and RWP installations have been completed to all elevations. 

Recent heavy rain has identified 2 leaks from the opening sashes of the recently installed roof lights. 1 in the hall and one in the corridor. The manufacturer is visiting site next week to make good the seals. 

The water and fire mains installations from the point of connection to the building is underway. A date for connection to the supply main remains to be agreed. 

The trenches for the lightning protection tapes are being excavated for BEST arriving on site w/c 22nd July. 

Bases for the ASHP and the SSE transformer have been cast this week. 

Taping & filling will be commencing on site w/c 22nd July. 

3 

Bats were witnessed during the 2nd survey. 1 or 2 bats were noted flying around outside and 1 inside. The millenium hall does not appear to be a maternity roost or require further surveys. The ecologist will report fully by the 10th of August. 

Preparations for 1st floor UFH installation are underway with insulation being laid. 

Trenches for lightning protection tapes are being dug. BEST due on site next wee 

Upcoming Activities 

Complete M&E 1st fix. Complete Fire capping edge seals over stair well. Install 1st floor UFH and screed the floor. Make good cladding finishes. Complete plasterboard to GF ceilings and partitions to GF areas. Progress internal Tape & Fill Progress external watermain and SSE power mains Install lightning tapes around building perimeter. 


  • The full report includes photos, tables and diagrams which can’t easily be separated from their original PDF format. Click HERE to view the full report.
  • An archive of these construction updates is available HERE.

 

At your convenience

Toilets openThe number of passing cyclists bodes well for when the new cafe opens but it’s a problem when they all want to use the community shop loo. We have therefore decided to make the Millennium Hall toilets available to the public between 8am and 8pm.

We request that user groups do not lock the hall door after their meeting. Jimmy or Steve will take care of opening and closing.

Strathdearn Community Hub : Construction Update #37

construction update smallDate : w/e 14th July 2019 

Weather : Temp 17°C, weather variable with periods of heavy rain. 

Principal Contractor : Compass Building & Construction Services Ltd 

Site Manager : Robbie Tewnion / Archie Cameron MacKintosh 

Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be 

determined by Client’s Representative. Site Personnel 

2 Site Manager 6 Joiners 0 Plasterer + 0 Apprentice 0 Mechanical (Crudens) 0 MH Electrical 0 Groundworkers 4 Scaffolders 0 Labourer 0 painters 2 Roofers 

Sub Contractors Appointed 

Shane MacLennan Groundworks EastWest Flooring Concrete Screed Scotframe Kit supply & design Swarco EV Charging Glulam Solutions Kit and glulam erection Standard Patent Glazing Roof Lights FP McCann Precast concrete supply C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation Highland Scaffolding Scaffolding Highland Decorating Taping & Decorating 

2 

Activities on site 

Labour numbers on site are lower than usual due to holidays. 

The blockwork forming the stair enclosure has been completed and the fireproof cap has been built. The perimeter of the capping has now been fire sealed to the viewing gallery side. The meeting room side remains to be fire stopped. Still the case. 

Diagonal bracing remains to be completed in the main hall. 

Roof slating, snow boards, Solar PV and solar hot water panels have been completed. 

Wall cladding is complete with window seals and timber ingos to be fitted. The upper level boards have been overcoated and the finish is looking far more even. Grilles have been installed over the smaller plenum boxes. 

Now that the scaffold has been dropped on the West elevation numerous paint runs on the low level narrow cladding boards can be seen. These will have to be flattened and re coated. Discussed with Chud and Archie on site who are aware and steps will be taken to make good 

1st fix electrical works are complete, back boxes are being fitted and sub mains boards being wired in. 

Plumbers have completed 1st fix plumbing and heating pipework runs above the shower and changing areas as well as above ceiling level at the Youth Group/ room room and Viewing Gallery/Lighting Control. The ceilings in the shower/changing areas are being insulated and sheeted. 

Exhaust and Fresh Air inlet Plenum boxes have been installed into the west elevation gable. Ducts remain to be run to the plenums or FAI’s in the hall. The air handling plant has been installed and ducting between the units is ongoing. 

M&E 1st Fix estimated as being 80% complete. 

Wall panels are being insulated in the corridor and main hall, The ceiling of the youth room has been sheeted. Some gaps between sheets are excessive. Ensure plasterboard sheets have been butted tight together. 

Main hall and access corridor plasterboarding is ongoing. Check fixing centres at sheets on ceilings. Should be 230mm generally and at 150mm centers at board ends. 

Gutter and RWP installations have been completed to West elevation. 

Recent heavy rain has identified 2 leaks from the opening sashes of the recently installed roof lights. 1 in the hall and one in the corridor. Compass are making contact with the manufacturer to notify them and get a resolution. 

Bats found during 1st survey. Further survey to be carried out end June / early july when weather allows. 

Joiners are installing the 2×2 and insulation at the 1st floor for the UFH system to be installed. 

Preparations for 1st floor UFH installation are underway with insulation being laid. 

3 

Upcoming Activities 

Complete M&E 1st fix. Drop remaining scaffolding. Complete Fire capping edge seals over stair well. Undertake 2nd bat survey to Millenium Hall. Install 1st floor UFH and screed the floor. Make good cladding finishes. Complete plasterboard to GF ceilings and erect partitions to GF areas. Progress internal Tape & Fill Start external watermain and SSE power mains


  • The full report includes photos, tables and diagrams which can’t easily be separated from their original PDF format. Click HERE to view the full report.
  • An archive of these construction updates is available HERE.

Strathdearn Community Hub : Construction Update #36

construction update smallDate : w/e 7th July 2019 

Weather : Temp 11 -16°C, 

Principal Contractor : Compass Building & Construction Services Ltd 

Site Manager : Robbie Tewnion / Archie Cameron MacKintosh 

Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be 

determined by Client’s Representative. Site Personnel 

2 Site Manager 7 Joiners 1 Plasterer + 1 Apprentice 2 Mechanical (Crudens) 3 MH Electrical 0 Groundworkers 0 Scaffolders 0 Labourer 2 painters 

Sub Contractors Appointed 

Shane MacLennan Groundworks EastWest Flooring Concrete Screed Scotframe Kit supply & design Swarco EV Charging Glulam Solutions Kit and glulam erection Standard Patent Glazing Roof Lights FP McCann Precast concrete supply C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation Highland Scaffolding Scaffolding Highland Decorating Taping & Decorating Activities on site 

2 

The blockwork forming the stair enclosure has been completed and the fireproof cap has been built. The perimeter of the capping has now been fire sealed to the viewing gallery side. The meeting room side remains to be fire stopped. 

The render and plaster to the inner face of the stair walls is complete. 

Diagonal bracing remains to be completed in the main hall. 

All window & glazed door installations are complete. Windows are being protected with temp adhesive film. 

Roof slating, snow boards, Solar PV and solar hot water panels have been completed. 

Wall cladding is almost complete with window seals and timber ingos to be fitted. The upper level boards have been overcoated and the finish is looking far more even. Base level boards are also substantially complete. Mechanical grilles remain to be fitted over plenums. 

Compass to confirm in writing that adidtional clips are not required to prevent wind uplift of the top apron. 

1st fix electrical works are complete, back boxes are being fitted and sub mains boards being wired in. 

Plumbers are ongoing with 1st fix plumbing and heating pipework runs above the shower and changing areas as well as above ceiling level at the Youth Group/ room room and Viewing Gallery/Lighting Control. One of the crimped pipe fittings at the main run above the viewing gallery looks like it may not have full insertion into the straight coupler. Shown to Robert for checking by the plumbers. Confirmed by plumbers as being robust. 

Exhaust and Fresh Air inlet Plenum boxes have been installed into the west elevation gable. Ducts remain to be run to the plenums or FAI’s in the hall. The air handling plant has been installed and ducting between the units is underway. 

Drain stacks have been installed to 1st floor level and SVP connections have been installed as roof slating progresses. 

M&E 1st Fix estimated as being 80% complete. 

Decoration of the walls and ceilings in plant area is ongoing 

Wall panels are being insulated in the corridor and main hall, The ceiling of the youth room was being sheeted at the time of the site visit. Some gaps between sheets are excesssive. Ensure plasterboard sheets have been butted tight together. 

Main hall and access corridor plasterboarding is ongoing. 

Gutter installations was just commencing on the front elevation. RWP’s have not yet been fitted. 

Bats found during 1st survey. Further survey to be carried out end June / early july when weather allows. 

3 

Upcoming Activities 

Progress & complete M&E 1st fix. Progress Joiner roughing. Progress wall cladding. Complete Fire capping edge seals over stair well. Complete roof slating to North elevation. Undertake 2nd bat survey to Millenium Hall. Gutters to main elevations.


  • The full report includes photos, tables and diagrams which can’t easily be separated from their original PDF format. Click HERE to view the full report.
  • An archive of these construction updates is available HERE.

Strathdearn Community Hub : Construction Update #35

construction update smallDate : 28th June 2019 

Weather : Temp 19°C, sunny 

Principal Contractor : Compass Building & Construction Services Ltd 

Site Manager : Robbie Tewnion / Archie Cameron MacKintosh 

Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be 

determined by Client’s Representative. Site Personnel 

2 Site Manager 8 Joiners 1 Plasterer + 1 Apprentice 2 Mechanical (Crudens) 3 MH Electrical 0 Groundworkers 4 Scaffolders 2 Tapers 0 Labourer 2 Roof slaters. 2 Best Lightning Specialists 6 Painters 

Sub Contractors Appointed 

Shane MacLennan Groundworks EastWest Flooring Concrete Screed Scotframe Kit supply & design Swarco EV Charging Glulam Solutions Kit and glulam erection Standard Patent Glazing Roof Lights FP McCann Precast concrete supply C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation Highland Scaffolding Scaffolding Highland Decorating Taping & Decorating 

2 

Activities on site 

The blockwork forming the stair enclosure has been completed and the fireproof cap has been built. The perimeter of the capping has now been fire sealed. 

The render and plaster to the inner face of the stair walls is almost complete. 

Diagonal bracing remains to be completed in the main hall. 

All window & glazed door installations are complete. Windows are being protected with temp adhesive film. 

Roof slating, snow boards, Solar PV and solar hot water panels have been completed. 

Roof verge flashings have been fitted at the gables. 

Wall cladding is ongoing. The upper level boards have been overcoated and the finish is looking far more even. Base level boards are ongoing. 

The rooflights have been re installed to ensure the lead integity at the base of the flashings. The base lead flashing has had stainless steel holding down clips added. The upper flashing does not have clips fitted. Compass have discussed with MacLeod Roofing to determine if additional clipes are required. Compass to confirm in writing that adidtional clips are not required to prevent wind uplift of the top apron. 

1st fix electrical works are progressing well with cable runs for lighting & small power substantially complete. 

Lightning tapes have been fitted across the roof. 

Plumbers are ongoing with 1st fix plumbing and heating pipework runs above the shower and changing areas as well as above ceiling level at the Youth Group/ room room and Viewing Gallery/Lighting Control. One of the crimped pipe fittings at the main run above the viewing gallery looks like it may not have full insertion into the straight coupler. Shown to Robert for checking by the plumbers who have confirmed it is secure. 

Exhaust and Fresh Air inlet Plenum boxes have been installed into the west elevation gable. Ducts remain to be run to the plenums or FAI’s in the hall. 

Drain stacks have been installed to 1st floor level and SVP connections have been installed as roof slating progresses. 

Glulam needs to be repaired below the 1st floor rooflight. The pin has split the timber, shown to Archie. 

Decoration of the walls and ceilings in plant area is underway. 

Wall panels are being insulated in the corridor and main hall, The ceiling of the youth room was being sheeted at the time of the site visit. Some gaps between sheets are excesssive and screws have been driven too far into the plasterboard. Ensure plasterboard sheets have been butted tight together and add additional screws where existing have driven too far through the surface. 

Bats found during 1st survey. Further survey to be carried out end June / early july when weather allows. 

3 

Upcoming Activities 

Progress & complete M&E 1st fix. Progress Joiner roughing internally Complete wall cladding externally. Complete Fire capping edge seals over stair well. Complete roof slating to North elevation. Progress tape and fill to internal plasterboard. Undertake 2nd bat survey to Millenium Hall. 


  • The full report includes photos, tables and diagrams which can’t easily be separated from their original PDF format. Click HERE to view the full report.