Work to upgrade the Balvraid Road (U2829) will be carried out during the summer of 2022. This is to aid timber extraction from Glenkirk Forest and is funded by the Scottish government’s Strategic Timber Transport Scheme (STTS).  Weekly schedules will be published here.

CLICK HERE to download map

U2829 Balvraid Road STTS              
Week Commencing              
10/10/2022 See ‘Balvraid STTS-Work Sectors’ for Sector locations
  Culverts Widening Surface Passing Places Patching Overlays Ditching Notes
Friday 07 Oct 2022   2          
Saturday 08 Oct 2022              
Sunday 09 Oct 2022              
Monday 10 Oct 2022   2          
Tuesday 11 Oct 2022   2/3          
Wednesday 12 Oct 2022   2/3          
Thursday 13 Oct 2022   2/3          
Friday 14 Oct 2022             No Works – Long weekend
Saturday 15 Oct 2022              
               
Notes on Delays              
Culverts Minor Delays – steel plates used to allow vehicles to cross
Widening Minor Delays – Improving passing opportunities, excavator on road
Surface Passing Places Moderate Delays – Paver and Lorries surfacing widened areas
Patching Moderate Delays – Planer removing surface / paver laying surfacing
Overlays Severe Delays – Once paver machine has started the lorry needs to empty and the surface cooled
Ditching Minor delays – excavator on road

Information supplied by:

Stuart Bell BSc CEng MICE
Senior EngineerArvikaconsult Ltd
stuart@arvikaconsult.co