Visit 02
Date : Friday 26th October.
Weather : Temp 3.5°C, sleet and rain
Principal Contractor : Compass Building & Construction Services Ltd
Site Manager : Robbie Tewnion & Jake Reid
Site Personnel
0 Site Manager 2 Demolition Contractors 0 Electrician 0 Ecologist
Sub Contractors Appointed
GF Job Demolition
Activities on site
Initial site establishment is in place. Toilets and welfare are available for use by site personnel.
The hall has now been demolished.
The tennis court has been grubbed up.
The remaining demolition spoil will be removed Monday.
Preparations to dismantle and remove the play equipment are underway.