Visit 03
Date : Thursday 1st November
Weather : Temp 5°C, clear, sunny
Principal Contractor : Compass Building & Construction Services Ltd
Site Manager : Robbie Tewnion & Jake Reid
Site Personnel
1 Site Manager
0 Demolition Contractors
0 Electrician
1 Lorry driver (to remove playpark equipment)
0 Ecologist
Sub Contractors Appointed
GF Job Demolition
Shane MacLennan Groundworks
Activities on site
Initial site establishment is in place. Toilets and welfare are available for use by site personnel.
The hall has now been demolished.
The tennis court has been grubbed up.
All spoil has been removed.
Playpark has been dismantled and removed off site for safe keeping. One or two timber elements will require to be replaced and Compass have retained fixings and a file of photos for use when re assembling the play equipment in the future.
Groundworks are starting on Monday 5th November.