Visit 13
Date : Friday 25th January 2019
Weather : Temp 0°C, Dry, sunny.
Principal Contractor : Compass Building & Construction Services Ltd
Site Manager : Robbie Tewnion & Jake Reid
Time Lost : 3 days lost to wet trades (3rd Dec 0°C, 4th Dec -1.5°C, & 5th Dec -7°C)
Compass to quantify any recent lost time due to temperature.
Site Personnel
1 Site Manager + 1 Trainee Site Manager 0 Pre cast installer 0 Crane 0 Ecologist 3 Groundworkers 0 Concrete Squad 0 Brick laying squad Site Engineer
Sub Contractors Appointed
Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Conscrete
2
Activities on site
Bolt pads have been stripped and Pads have been put back over the bolts to keep the pockets clean and free of debris.
The 1st lift of blockwork forming the stair enclosure has been built. Low temperatures are hampering progress on site. Compass are looking at an alternative to the concrete blocks and cap slabs above 1st floor. An amendment to warrant will be required due to proposed change in fire proofing the stairwell.
The GF Slab has been poured and is complete. Much of the slab is covered in snow and ice however it was noted that the areas of exposed slab are suffering from a degradation of the surface. Possibly due to low temperatures overnight after the pour. See photos below. Proposals required from Compass as to how the issue will be rectified.
No further works on the building have taken place since the last report.
Carpark upfill is ongoing.
Upcoming Activities
Complete escape stair blockwork and cap slab.
Glulam delivery scheduled for 28th January now. May move back depending on progress, weather and temperatures. Blockwork construction to stairwell is on the critical path since the cap slab needs to go on before glulam is installed.
Progress car park works.