construction update smallDate : Wednesday 6th & 8th March 2019

Weather : Temp 8°C, Dry, light breeze on 6th March, Raining on 8th March.

Principal Contractor : Compass Building & Construction Services Ltd

Site Manager : Robbie Tewnion & Jake Reid

Time Lost : 22.75 days lost to weather by PC’s calculation.

Delay to contract to be determined by Client’s Representative.

Site Personnel

1 Site Manager + 1 Trainee Site Manager 1 Forklift Driver 1 Crane 2 Glulam Erection Squad 0 Groundworkers 0 Concrete Squad 0 Brick laying squad 1 Labourer

Sub Contractors Appointed

Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation

2

Activities on site

The 1st lift of blockwork forming the stair enclosure has been built. Low temperatures are hampering progress on site. Compass are looking at an alternative to the concrete blocks and cap slabs above 1st floor. An amendment to warrant will be required due to proposed change in fire proofing the stairwell. Fairhurst/Makar design & Building Warrant amendment submission is ongoing. @rhonadonnely

The GF Slab has been poured and is complete. Proposals required from Compass as to how the GF slab issues will be rectified.

Glulam erection is complete with exception of roof structure. The main posts and tie beams have been erected and braced with temporary props. Gf Panel installation is complete.

Floor cassettes have been installed and 1st floor panel installation is complete.

Roof trusses are being assembled on the deck ready for lifting into position.

Diagonal bracing remains to be fitted to the columns however the temporary bracing is still in place.

The kit and glulam installation looks to be of a good quality. Fixings are at very tight centres so no concerns with regard to nailing.

It was noted a that a few JJI’s have the web blocking pieces missing at the bearing points. All other JJI’s have blocking pieces fitted. The matter was discussed on site with the erection squad and they undertook to install any missing blocking pieces. The missing blocking pieces are as per kit installation details. Not required.

Carpark works have been suspended for now. Area required for sturctural frame and kit deliveries.

Upcoming Activities

Kit deliveries are ongoing with deliveries scheduled for the 12th and 15th March. The 1st load of roof cassettes has been delivered to site. The roof cassette delivery is due 12th March.

Windows are stored locally off site for installation when ready.

Plasterboard deliveries scheduled for 8th April.

Fire capping at the stair is with Makar just now for warrant amendemnt submission.

Progress car park works once structural frame and panels have been completed and the car park area has been cleared.

Pre start meeting with Scottish Water was held on Tuesday 4th March and the road closure for drainage connection is booked for the 11th March with road closure at the site booked in on the 18th March for 3 weeks.

Electricians & plumbers are booked in provisionally for w/c 25th March for 1st fix M&E.