construction update smallDate : Thursday 4th April 2019

Weather : Temp 3°C, Sleet, cold & wet

Principal Contractor : Compass Building & Construction Services Ltd

Site Manager : Robbie Tewnion & Jake Reid, Archie Cameron MacKintosh

Time Lost : 26.5 days lost to weather by PC’s calculation. Delay to contract to be

determined by Client’s Representative. Site Personnel

2 Site Manager + 1 Trainee Site Manager 1 Forklift Driver 1 Crane 3 Glulam Erection Squad 0 Engineer 3 Groundworkers 0 Bricklaying squad 1 Labourer

Sub Contractors Appointed

Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation

2

Activities on site

The 1st lift of blockwork forming the stair enclosure has been built. Low temperatures are hampering progress on site. Compass are looking at an alternative to the concrete blocks and cap slabs above 1st floor. An amendment to warrant will be required due to proposed change in fire proofing the stairwell. Fairhurst/Makar design & Building Warrant amendment submission is ongoing.

The GF Slab has been poured and is complete. Proposals awaited from Compass as to how the GF slab issues will be rectified.

Glulam erection is complete. The main posts, tie beams and trusses have been erected and Gf & 1st floor Panel installation is complete.

Roof cassettes installation is ongoing (70% Complete) however heavy snow and winds this week have again slowed up construction and erection of the structural kit.

Diagonal bracing remains to be fitted to the columns however some temporary bracing is still in place.

The kit and glulam installation looks to be of a good quality. Fixings are at very tight centres so no concerns with regard to nailing.

Columns have been grouted into place and base course render has commenced. The Holding down straps have been installed at relevant centres and at the sides of each opening. Re inforcement mesh panels were bing installed over the HD Straps to prevent cracking in the render.

The offsite drainage is up to within a few metres of F1 but works were halted on the 3rd April due to snow. The offsite drainage should be complete by 5th April with surfacing to be arranged w/c 8th April. All the above are weather permitting. Scottish Water will be called back to site to inspect finished manholes and Compass will be arranging a cctv survey of the drain to allow formal adoption.

Carpark works have been suspended for now. Area still required for structural frame and kit laydown.

3

Upcoming Activities

Kit deliveries are substantially complete.

Windows are stored locally off site for installation, Hopefully to commence w/c 8th April.

Plasterboard deliveries scheduled for 8th April may now be delayed a further week.

Fire capping at the stair is with Makar just now for warrant amendment submission.

Progress car park works once structural frame and panels have been completed and the car park area has been cleared.

Complete the offiste drainage works and re surface the road.

Electricians & plumbers were booked in provisionally for w/c 25th March for 1st fix M&E however this has been put back to w/c 8th April to allow the building to be made wind and watertight.


  • The full report includes photos, tables and diagrams which can’t easily be separated from their original PDF format. Click HERE to view the full report.