[This article is published at the request of SSEN]

Scottish and Southern Electricity Networks Knocknagael – Tomatin Project
Construction works in and around your area – Safety is always our first priority at Scottish and Southern Electricity Networks (SSEN) and with this in mind, we ask that you please remain vigilant of signage or direction around the construction works and do not enter our working areas. Users of the access tracks are asked to obey signage and are reminded that large vehicles and construction traffic are also using the tracks.
Tomatin Substation
The substation was fully energised last autumn. The site cabins have been removed and final reinstatement and fencing works will be completed in March 2020.
The final planting and seeding will also complete in March 2020.
Interface works at Boat of Garten substation are complete with the focus now having moved to Farr substation with a small specialised team.







