Balfour Beatty are removing the “kink” in the Tomatin access road as it has now served its purpose for their works. They will shift the Tomatin junction slightly south (less than 20-metres), aiding construction of the new northbound carriageway while also avoiding road closures for the community. This will require three-way temporary traffic signals on the A9 and Tomatin access road overnight from 19:00 on 3 December until 06:00 on 4 December.
[From Gemma Corbett, Community Liaison Officer, Balfour Beatty]
The construction of the new northbound carriageway between Tomatin and Dalmagarry is progressing well.
To support the next phase of construction, we will be slightly adjusting the Tomatin access road and junction onto the A9 with a new layout effective from Friday 4 December. These changes will remain in place until early 2027.

What you need to know:
• From 4 December, the Tomatin access junction will be located less than 20 metres south of its current position.
• The existing bend on the Tomatin access road will be removed.
• The revised road layout will remain in place until early 2027, when traffic is switched from the existing A9 onto the new northbound carriageway.
• To allow these changes to be carried out safely, three-way temporary traffic signals will operate on the A9 and Tomatin access road overnight from 19:00 on 3 December until 06:00 on 4 December.
• The new traffic management measures will be clearly signposted for road users and non-motorised users.
To minimise delays, the temporary traffic signals will be manually operated.
Pedestrian and emergency service access will be maintained at all times.
Please note that all works are weather dependent and may be subject to change. For the latest information, visit: A9Dualling.scot/roadworks.
[If you have any questions, please email A9T2M@balfourbeatty.com]