“Temporary traffic signals and a short 200m lane closure will be implemented on the A9 near Moy Rail Bridge and the current realignment in place at Lynebeg. for approximately two weeks from Monday 3 November 2025 between the hours of 07:30 and 21:30.
There will be no work carried out on Saturday or Sundays. This is to facilitate culvert installations and sheet piling.
More information on this can be found here: https://www.a9dualling.co.uk/a9-dualling/roadworks/a9-tomatin-to-moy-temporary-traffic-signals-on-a9-near-moy-rail-bridge/”