Visit 05
Date : Friday 16th November
Weather : Temp 5°C, clear, sunny
Principal Contractor : Compass Building & Construction Services Ltd
Site Manager : Robbie Tewnion & Jake Reid
Site Personnel
1 Site Manager + 1 Trainee Site Manager 0 Electrician 1 Lorry driver removing spoil 0 Ecologist 3 Groundworkers 1 Site Engineer
Sub Contractors Appointed
Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer
Activities on site
Initial site establishment is in place. Toilets and welfare are available for use by site personnel.
Soil has been stockpiled on site and being removed.
Foundations have commenced. Dowel bars to be drilled in at some junctions. Ensure dowel embedment depth is to engineer’s design.
Where mesh tails have been left for overlapping mesh to be tied to ensure sufficient lap length (350mm minimum or 2 squares of mesh) to be left for next section to be tied to.
Substructure blockwork is now due to commence Wednesday 21st November.
[The full report includes photos and diagrams which can’t easily be separated from their original PDF format. Click HERE to view the full report.]