Date : Friday 30th November
Weather : Temp 4.5°C, Heavy rain with sunny spells.
Principal Contractor : Compass Building & Construction Services Ltd
Site Manager : Robbie Tewnion & Jake Reid
Site Personnel
1 Site Manager + 1 Trainee Site Manager 0 Electrician 0 Lorry driver removing spoil 0 Ecologist 3 Groundworkers 0 Brick laying squad 0 Site Engineer
Sub Contractors Appointed
Shane MacLennan Groundworks Scotframe Kit supply & design Glulam Solutions Kit and glulam erection FP McCann Precast concrete supply & install. C MacPhee Bricklayer
Activities on site
Initial site establishment is in place. Toilets and welfare are available for use by site personnel. Foundations have commenced.
Substructure blockwork is now substantially complete with spaces left for casting the extensions for the Glulam HD bolt pads.
Dowels for tying the pad extensions to the pad founds remain to be installed.
Shuttering for the pad extensions remains to be installed.
Fairhurst have been consulted regarding subsoil percolation rates. Fairhurst have confirmed ground conditions are as expected and soakaways can proceed as per the design.