Date : 12th June 2019
Weather : Temp 9°C, raining
Principal Contractor : Compass Building & Construction Services Ltd
Site Manager : Robbie Tewnion / Archie Cameron MacKintosh
Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be
determined by Client’s Representative. Site Personnel
2 Site Manager 10 Joiner / Labourer 2 Mechanical (Crudens) 2 MH Electrical 0 Groundworkers 2 Scaffolders 0 Labourer 3 Roof slaters. 2 Patent Glazing
Sub Contractors Appointed
Shane MacLennan Groundworks EastWest Flooring Concrete Screed Scotframe Kit supply & design Swarco EV Charging Glulam Solutions Kit and glulam erection Standard Patent Glazing Roof Lights FP McCann Precast concrete supply C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation Highland Scaffolding Scaffolding Highland Decorating Taping & Decorating
2
Activities on site
The blockwork forming the stair enclosure has been completed to cap slab level. Materials for ceiling now on site and joists to support the ceiling were being installed onto Joist hangers.
Diagonal bracing 90% completed with 1 bay of highlevel bracing in the main hall still to be fitted.
All window & glazed door installations are complete. Windows are being protected with temp adhesive film.
The South elevation of the roof has been slated and the snow board clips installed. Slate flakes and chips have been mostly cleaned off the roof. Roofers are still slating the north elevation following the re installation of the rooflights and lead bottom flashings as noted in the previous report.
1st fix electrical works are progressing well with cable runs for lighting & small power substantially complete.
Plumbers are ongoing with 1st fix plumbing and heating pipework runs above the shower and changing areas.
Exhaust and Fresh Air inlet Plenum boxes have been installed into the west elevation gable
Drain stacks have been installed to 1st floor level and SVP connections have been installed as roof slating progresses.
Battens and counter battens for wall cladding are complete. Cladding installation has commenced at the west gable elevation.
Fixing bars for the solar panels are being assembled inside ready for installation with the roof slating.
Glulam needs to be repaired below the 1st floor rooflight. The pin has split the timber.
Plasterboarding of ceiling in plant area is ongoing.
Upcoming Activities
Progress & complete M&E 1st fix. Progress Joiner roughing. Progress wall cladding. Complete Fire capping over stair well. Complete roof slating to North elevation. Undertake bat survey to Millenium Hall w/c 10th June weather permitting.