Work to upgrade the Balvraid Road (U2829) will be carried out during the summer of 2022. This is to aid timber extraction from Glenkirk Forest and is funded by the Scottish government’s Strategic Timber Transport Scheme (STTS). Weekly schedules will be published here.
CLICK HERE to download map
| Culverts | |||||||
| Week Commencing | |||||||
| 15/08/2022 | See ‘Balvraid STTS-Work Sectors’ for Sector locations | ||||||
| Culverts | Widening | Surface Passing Places | Patching | Overlays | Ditching | Notes | |
| Friday 12 Aug 2022 | |||||||
| Saturday 13 Aug 2022 | |||||||
| Sunday 14 Aug 2022 | |||||||
| Monday 15 Aug 2022 | |||||||
| Tuesday 16 Aug 2022 | 1 | 1 | Mobilise plant to site | ||||
| Wednesday 17 Aug 2022 | 1 | 1 | |||||
| Thursday 18 Aug 2022 | 1 | 1 | |||||
| Friday 19 Aug 2022 | 1 | 1 | |||||
| Saturday 20 Aug 2022 | |||||||
| Notes on Delays | |||||||
| Culverts | Minor Delays – steel plates used to allow vehicles to cross | ||||||
| Widening | Minor Delays – Improving passing opportunities, excavator on road | ||||||
| Surface Passing Places | Moderate Delays – Paver and Lorries surfacing widened areas | ||||||
| Patching | Moderate Delays – Planer removing surface / paver laying surfacing | ||||||
| Overlays | Severe Delays – Once paver machine has started the lorry needs to empty and the surface cooled | ||||||
| Ditching | Minor delays – excavator on road |
~~~~~~~~~~~~~~~~~~~~~~
Stuart Bell BSc CEng MICE
Senior EngineerArvikaconsult Ltd