Work to upgrade the Balvraid Road (U2829) will be carried out during the summer of 2022. This is to aid timber extraction from Glenkirk Forest and is funded by the Scottish government’s Strategic Timber Transport Scheme (STTS). Weekly schedules will be published here.
CLICK HERE to download map
Stuart Bell, who supplies these schedules, is on holiday for 2 weeks and supplied 2 weeks’ worth before he left. This schedule below is dependent on there having been no unexpected delays in last week’s work programme. Stuart explains: “May vary with the weather and progress, but minimal delays expected. Civils squads doing the widening hope to complete by the 21st October. The surfacing squad is expected towards the end of the month (which is when the significant disruption is most likely), for about 4 weeks. Hopefully the weather will be favourable and allow the surfacing to complete without delays.”
| U2829 Balvraid Road STTS | |||||||
| Week Commencing | |||||||
| 17/10/2022 | See ‘Balvraid STTS-Work Sectors’ for Sector locations | ||||||
| Culverts | Widening | Surface Passing Places | Patching | Overlays | Ditching | Notes | |
| Friday 14 Oct 2022 | No Works – Long weekend | ||||||
| Saturday 15 Oct 2022 | |||||||
| Sunday 16 Oct 2022 | |||||||
| Monday 17 Oct 2022 | No Works – Long weekend | ||||||
| Tuesday 18 Oct 2022 | 3/4/5 | ||||||
| Wednesday 19 Oct 2022 | 3/4/5 | ||||||
| Thursday 20 Oct 2022 | 3/4/5 | ||||||
| Friday 21 Oct 2022 | 3/4/5 | Civils works may be complete | |||||
| Saturday 22 Oct 2022 | |||||||
| Notes on Delays | |||||||
| Culverts | Minor Delays – steel plates used to allow vehicles to cross | ||||||
| Widening | Minor Delays – Improving passing opportunities, excavator on road | ||||||
| Surface Passing Places | Moderate Delays – Paver and Lorries surfacing widened areas | ||||||
| Patching | Moderate Delays – Planer removing surface / paver laying surfacing | ||||||
| Overlays | Severe Delays – Once paver machine has started the lorry needs to empty and the surface cooled | ||||||
| Ditching | Minor delays – excavator on road | ||||||
Information supplied by:Stuart Bell BSc CEng MICE
Senior EngineerArvikaconsult Ltd
stuart@arvikaconsult.co
Senior EngineerArvikaconsult Ltd
stuart@arvikaconsult.co