These issues are separate to the ones posted about yesterday regarding possible delays while huge beams are transported for Dalmagarry Bridge. These ones relate to traffic management changes flagged last week. They begin tomorrow and Balfour Beatty want to remind you of this. Here’s a summary, with a link to the original post:
From 28 August 2026, traffic management on the A9 just north of the current Tomatin to Moy roadworks, south of Daviot, will be extended by around 2.5km towards Inverness for up to four weeks, with a temporary 40mph speed limit and one lane maintained in each direction. Some delays are possible, particularly during a small number of overnight works, although these are expected to be kept to a minimum.
For full details read the original post:
https://strathdearn.org/2026/08/17/a9-roadworks-temporarily-extended-in-late-august/