[Last November, timber haulage from Glenkirk was suspended after breaches of the agreed Timber Traffic Management Plan (TTMP). SCC requested a review of the TTMP for 2026 with Roundwood Transport Services (RTS) who manage transport, planning and scheduling for forest owners. RTS have responded with the following letter]
There are still around 3600 tonnes sat at roadside within Glenkirk, which equates to roughly 150 lorry movements or 5 weeks of haulage. I would like this to be cleared before we do any further haulage (April to May).
A tender has gone out for this years harvesting program, in which we are proposing to fell 27ha, giving a volume of around 8500. This would equate to 3 months haulage at full capacity but invariably this will run over, and I suspect we would be looking for the haulage to be completed by the middle of September (May – Sept). The proposed harvesting this year will be very dependant on the timber market, which is suppressed.
My RTS colleague Emily Gerrard, who has been dealing with the forest management within Glenkirk for several years, and she would be the RTS representative and make any necessary changes to the TTMP that the community deem fit. As an example weekend haulage needs to be included, to close out a current perceived grey area.