Strathdearn News
Hire rates for the new hall facilities – an explanation
During the last few Community Council Meetings the subject of the charge rate for the new hall facilities has attracted significant attention. The Strathdearn Community Development Company (SCD) are now in a position to publish the proposed charge out rates for the use of the various amenities. You will note...
Read More
Community Council Election Poster 2019
There will soon be several vacancies in the Community Council. If not enough people come forward, Highland Council will take over administration of Strathdearn affairs and we will have very little say in the decisions that affect us. Read below to learn all about becoming a candidate. ...
Read More
Minor road disruption 16-20 Sep – Traffic lights outside the hall.
Compass will be tarring the hall car park and access road into the car park next week. A set of traffic lights will be set up either side of the entrance into the site and will be in place for most of the week. They will be down for the...
Read More
Strathdearn Community Hub : Construction Update #45
Date : w/e 8th Sept 2019 Weather : Temp 15°C, variable with rain Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined by Client’s Representative. Site Personnel ...
Read More
Strathdearn CC – Agenda for meeting on 10th September
STRATHDEARN COMMUNITY COUNCIL MEETING on TUESDAY 10 September 2019 At 7:30pm IN THE STRATHDEARN HALL, TOMATIN PLEASE NOTE: THE ITEM ON THE EXTRACTION OF TIMBER FROM GLENKIRK HAS BEEN POSTPONED AGAIN. SANDY PRINGLE HAS NOT YET RECEIVED THE SURVEY OF THE ROAD FROM HIGHLAND COUNCIL. HOPEFULLY THIS WILL HAVE BEEN...
Read More
Strathdearn Community Hub : Construction Update #44
Date : w/e 1st Sept 2019 Weather : Temp 15°C, variable with rain Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined by Client’s...
Read More
Help plan our future – Millennium Hall, Sep 5, 7-9 pm
Duncan Bryden, Director at Strathdearn Community Developments has kindly 'volunteered' to run a 'Planning for Real' exercise for Strathdearn. The 2011 Strathdearn Community Plan and the 2014 Inner Moray Firth Local Development Plan are up for renewal. You are invited to look at plans and maps of the area and...
Read More
Strathdearn Community Hub : Construction Update #43
Date : w/e 25th August 2019 Weather : Temp 15°C, warm and predominantly dry Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined by...
Read More
HUB AND EVENTS MANAGER AND FACILILTIES SUPERVISOR REQUIRED
Two exciting new posts have arisen to work as a Hub and Events Manager and Facilities Supervisor for White River Trading (WRT) the trading arm of Strathdearn Community Development Company. Hub and Events Manager The position on offer is 35 hours per week (a job share may...
Read More
Road Closure – Shop Brae – commencing 2nd September
Most of the Shop Brae Road (from the sewage treatment works to the road end of Tomatin House) will be closed to traffic for 6 weeks from 2nd September. Apparently Network Rail closed the same bit of road in July to do work on the railway viaduct but didn't finish...
Read More
ART IN STRATHDEARN'S ANNUAL ART EXHIBITION, 2019
ART IN STRATHDEARN'S ANNUAL ART EXHIBITION will be held next Friday 23rd to Sunday 25th in the hall. Free entry & parking Preview Friday August 23rd 7pm to 9pm - Everyone welcome. Saturday August 24th : 11am to 5pm Sunday August 25th : 11am to 5pm Lots to see...
Read More
Strathdearn Community Hub : Construction Update #41
Date : w/e 11th August 2019 Weather : Temp 17°C, warm and predominantly dry with occasional showers. Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to...