Strathdearn Community Hub : Construction Update #32
Date : 4th & 6th June 2019 Weather : Temp 9°C, heavy rain Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined by Client’s...
Read More
Strathdearn Community Hub : Construction Update #31
Date : 30th May 2019 Weather : Temp 14°C, light rain, heavier in morning Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined by...
Read More
Strathdearn Community Hub : Construction Update #30
Date : 23rd May 2019 Weather : Temp 14°C, dry, light cloud cover, heavy rain earlier in the week. Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to...
Read More
Strathdearn Community Hub : Construction Update #29
Date : 15th & 17th May 2019 Weather : Temp 14°C, dry, light cloud cover Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined...
Read More
Strathdearn Community Hub : Construction Update #28
Date : Friday 10th May 2019 Weather : Temp 9°C, dry, light cloud cover Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined by...
Read More
Strathdearn Community Hub : Construction Update #27
Date : Tuesday 30th April 2019 Weather : Temp 14°C, sunny, dry, light cloud cover Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined...
Read More
Strathdearn Community Hub : Construction Update #26
Date : Friday 26th April 2019 Weather : Temp 11°C, dry / cloudy Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion / Archie Cameron MacKintosh Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be determined by Client’s...
Read More
Easter Services
The Church of Scotland: The Parish of Moy, Dalarossie & Tomatin linked with Daviot & Dunlichity Easter – 2019 Good Friday Service (19th April) 7pm in the Strathdearn Hall A Joint Service with Daviot & Dunlichity – A Reflective Time of Bible Readings, Hymns, Prayers and Meditations led...
Read More
Strathdearn Community Hub : Construction Update #24
Date : Thursday 11th April 2019 Weather : Temp 12°C, dry / sunshine Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion Time Lost : 26.5 days lost to weather by PC’s calculation. Delay to contract to be determined by Client’s Representative. Site Personnel 1...
Read More
Friendship letter to Tomatin from Waltersburg
The following letter was sent to Strathdearn Community Council. It is just too nice NOT to share! Waltersberg, March 2019 The winter has now passed and the spring has taken over. And the first daffodil and crocus flowers are blooming in Waltersberg. Not long now and the whole village will...
Read More
Strathdearn Community Hub : Construction Update #23
Date : Thursday 4th April 2019 Weather : Temp 3°C, Sleet, cold & wet Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion & Jake Reid, Archie Cameron MacKintosh Time Lost : 26.5 days lost to weather by PC’s calculation. Delay to contract to be...
Read More
Traffic lights for a little longer
Apologies to everyone affected, especially those living in houses alongside the roadworks, but we've just learned that due to the recent snowy weather, the work will continue until the middle of next week. This shouldn't affect the closure dates for the Millennium Hall. If there are any further updates, we'll...
Read More
Strathdearn Community Hub : Construction Update #22
Date : Friday 29th March 2019 Weather : Temp 8°C, Sunny, Moderate / light winds Principal Contractor : Compass Building & Construction Services Ltd Site Manager : Robbie Tewnion & Jake Reid Time Lost : 26.5 days lost to weather by PC’s calculation. Delay to contract to be determined by...
Read More