Date : 20th June 2019
Weather : Temp 13°C, dry, overcast
Principal Contractor : Compass Building & Construction Services Ltd
Site Manager : Robbie Tewnion / Archie Cameron MacKintosh
Time Lost : 30.25 days lost to weather by PC’s calculation. Delay to contract to be
determined by Client’s Representative. Site Personnel
2 Site Manager 13 Joiners 1 Plasterer + 1 Apprentice 3 Mechanical (Crudens) 0 MH Electrical 0 Groundworkers 0 Scaffolders 2 Tapers 0 Labourer 2 Roof slaters. 0 Patent Glazing
Sub Contractors Appointed
Shane MacLennan Groundworks EastWest Flooring Concrete Screed Scotframe Kit supply & design Swarco EV Charging Glulam Solutions Kit and glulam erection Standard Patent Glazing Roof Lights FP McCann Precast concrete supply C MacPhee Bricklayer Gartec Lift supplier & installer. Andrew Cowie Concrete slab installer FP McCann Precast Concrete McLeod Roofing Slate Roofing MH Electrical Electrical Installation RI Cruden Mechanical Installation Highland Scaffolding Scaffolding Highland Decorating Taping & Decorating
2
Activities on site
The blockwork forming the stair enclosure has been completed and the fireproof cap has been built. The perimeter of the capping needs to be fire sealed. Suggested using off cuts of fire rated plasterboard and fire mastic.
The render to the inner face of the stair walls has commenced.
Diagonal bracing remains to be completed.
All window & glazed door installations are complete. Windows are being protected with temp adhesive film.
The South elevation of the roof has been slated and the snow board clips installed. Slate flakes and chips have been mostly cleaned off the roof. Roofers are still slating the north elevation. The solar PV installation is ongoing, Solar hot water panels have not yet been installed.
Roof verge flashings have been fitted at the gables.
The rooflights have been re installed to ensure the lead integity at the base of the flashings. The base lead flashing has had stainless steel holding down clips added. The upper flashing does not have clips fitted. Compass to discuss with MacLeod Roofing and determine if additional clipes are required. See photo below.
1st fix electrical works are progressing well with cable runs for lighting & small power substantially complete.
Plumbers are ongoing with 1st fix plumbing and heating pipework runs above the shower and changing areas as well as above ceiling level at the Youth Group/ room room and Viewing Gallery/Lighting Control.
Exhaust and Fresh Air inlet Plenum boxes have been installed into the west elevation gable
Drain stacks have been installed to 1st floor level and SVP connections have been installed as roof slating progresses.
Battens and counter battens for wall cladding are complete. Cladding installation is ongoing. The gaps and nailing to the lower boards are not uniform, see photos below. There are paint runs and large variations in shades of grey on the cladding boards that will need to be addressed. The mesh behind the panels will need to be protected from paint splashes when applying the final coats of cladding paint.
Glulam needs to be repaired below the 1st floor rooflight. The pin has split the timber.
Plasterboarding of ceiling in plant area is being taped and filled. The walls and ceiling in the Store area have been sheeted and joint taping/filling is almost complete.
Wall panels were being insulated in the corridor and main hall, insulation was also being installed in the ceiling below the Youth Room.
Bats found during 1st survey. Further survey to be carried out end June / early july when weather allows.
Joiners are assembling the shutter for the power transformer base to be cast externally.
3
Upcoming Activities
Progress & complete M&E 1st fix. Progress Joiner roughing. Progress wall cladding. Complete Fire capping edge seals over stair well. Complete roof slating to North elevation. Undertake 2nd bat survey to Millenium Hall.